| SCOPE OF WORK
Supply of perforated metal panel
work on wall including the necessary acoustical insulation,
furring channels and all related fasteners, trims and
flashing as per HESCO standard details and shop drawings.
PRODUCTION
DESCRIPTION
Variquiet, field Assembled
Acoustical Wall Panel System having a perforated metal liner
and acoustical insulation fixed on hat shape furring
channels.
METAL PANELS
Perforated steel panels, 305 mm
wide, formed from galvanized steel sheets gage 0.60 mm to
0.75 mm and conforming to ASTM A446 structural quality with
hot dipped commercial quality galvanization designation
G-90.
Perforation shall be in diameter
3mm and spaced 10mm staggered to achieve noise reduction
coefficient (NRC) of 0.95 or better.
Side joint shall be in male/female
interlocking type formed from solid material. Side joints
shall be formed as per HESCO standard details and shall be
sealed using a special EPDM neoprene gasket.
Panel finish shall be in high
quality multi-layered baked coating having HESCO standard
bone white colour at the exposed face and a standard wash
coat at the back face. The finish type and specifications
shall be one of HESCO standard coating which is polyester
finish for internal or Kynar PVF-2 for external use or
depending on the application
ACOUSTICAL INSULATION
Fiberglass blanket insulation,
approximately 38 - 50 mm thick and have special properties
to achieve NRC value of 0.95 or better and shall be foil
faced or vinyl backed at one side. Wire mesh spacer made of
galvanized steel mesh approximately 25 x 25 mm shall be used
between perforated sheets and acoustical insulation.
FURRING CHANNELS
Hat shape galvanized steel
conforming to ASTM A446 designation G-90 having a gage of
approximately 0.7 mm or as recommended by HESCO. depth,
girth and spacing of furring channels shall be as per HESCO
standard details and recommendation.
VARIQUIET INSTALLATION
INSTRUCTION
1. Securely fasten
hat-shaped furring channel to walls using special concrete
fasteners as per HESCO standard and recommendation.
2. Install
perforated metal panels plumb in proper alignment level to
within a ratio of 1 to 500 and in strictly accordance with
HESCO shop drawings and instructions. Arrange panels
symmetrically on each surface, unless otherwise indicated
lay wire mesh spacer in perforated panels before placing
acoustical insulation to keep insulation slightly back from
perforated face.
3. Acoustical
insulation shall be a snug fit in perforated panels.
4. Cut metal
panels shall be at least 50 percent of unit width. Scribe
panels to fit adjacent work. Apply trim and fastenings as
per HESCO standard details and recommendation.
FASTENERS
Concealed fastening system using
stainless steel fasteners to fix panels to furring channels
and stainless steel pop rivets for fix the necessary
flashing shall be provided by HESCO as per HESCO engineering
details and standard practice.
TRIMS AND FLASHING
using solid material having the
same gage, finish and matching colour as that of the
perforated panels. flashing location, girth and fixing
details shall be in accordance with HESCO standard
engineering details.
|